Power
Division is set to establish a liaison office at Japan or Singapore to
complete the tendering process of 2x600 MW Matarbari coal fired power
project, the country's biggest ever power project funded by Japan
government.
State Minister for Power, Energy and Mineral Resources
Nasrul Hamid made this offer on Thursday to the Japanese Ambassador in
Dhaka Masato Watanabe as the selected bidders are not willing to visit
Bangladesh right now due to security ground. However, about 43 Japanese
nationals are now working in this project.
Two Japanese
bidders-Marubeni Corporation and Sumitomo Corporation-were shortlisted
following their submission of expression of interest (IOE). But they did
not like to visit Bangladesh right at the moment.
Japanese donor
agency-Japan International Cooperation Agency (JICA)-has been financing
the mega project of 1200 MW of power plant with a financial loan support
of $3.7 billion at an annual interest rate of 0.1 percent over 30
years, also having an initial ten-year grace period.
"We need to
expedite the job as soon as possible as we are already delayed to
complete the job," a senior official told the Daily Observer on
Thursday.
The tender process for Matarbari 2X600MW Ultra Super
Critical Coal- Fired Power Plant has been put on hold as the Japanese
contractors are unwilling to visit Bangladesh right now on security
grounds, according to a Japanese daily news report.
Toshiba
Corporation and Mitsubishi Hitachi Power System Ltd were expected to
take part in the tender on July 24, 2016; however, they have requested
the Bangladeshi counterpart to delay the process for one month,
according to the Coal Power Generation Company Bangladesh Ltd.
Earlier,
the Japan Times reported that the tender process has been stopped due
to security reasons in the wake of the Gulshan terror attack.
As many
as 20 people, including 17 foreigners were killed in the July 1 attack
at the Holey Artisan Bakery and O' Kitchen Restaurant.
Seven Japanese nationals were among those killed. They were surveyors for the Dhaka metrorail project.
As
per schedule the construction work of the country's largest coal-fired
power plant was to begin within eight to nine months' time following
completing the tendering process, according to an official.
Japan
International Cooperation Agency (JICA) is supposed to provide US $3.7
billion for the project. According sources at the Economic Relations
Division (ERD), the company will borrow $3.7 billion from JICA at an
annual interest rate of 0.1 per cent for the next 30 years, with an
initial 10-year grace period.
Earlier, the Executive Committee of the
National Economic Council (ECNEC) approved the Matarbari 2X600MW Ultra
Super Critical Coal Fired Power Plant project involving Taka 35,984.46
crore and aimed at boosting power generation significantly.
"Now the
work process would be delayed by at least 6 months," an official said.
As per schedule the construction work of the power plant was supposed to
begin within eight to nine months.
The entire project is scheduled
to be completed by June, 2023. The power plant will possess highest
thermal efficiency in the world at 41.3 per cent compared to 36 per cent
in the USA, 29 per cent in India, the UK and Germany, 38 per cent in
France and 40 per cent in Japan. The project also includes a deep-sea
port near the plant for handling coal imports for the plant.
The
government is implementing the Matarbari project as a priority one with
the targeting to start its implementation in January 2017, while
operation in 2023.