The Bangladesh Bridge Authority (BBA) has sought an explanation from the operator of the Dhaka Elevated Expressway over alleged irregularities in toll collection and the involvement of a Chinese company in operating and maintaining the facility without proper approval.
The authority is also planning to deploy personnel at all 22 toll lanes to manually count vehicles and verify traffic figures amid allegations that the number of vehicles using the expressway has been understated, potentially resulting in revenue losses.
In a letter dated November 18, the BBA asked First Dhaka Elevated Expressway Company Limited (FDEEC) to submit written explanations and supporting documents on three issues within seven working days. Failure to do so could lead to contractual and legal action.
Project Director Mohammad Golam Mortuza confirmed the development on Thursday night, saying the authority had invited tenders to recruit personnel for manual vehicle counting across all 22 lanes.
One major concern involves the role of China's Shandong Hi-Speed International Operation and Maintenance Private Limited in toll collection and expressway operations. The BBA said these activities appeared to exceed the scope approved by the Bangladesh Investment Development Authority (BIDA).
BIDA had authorised the company to operate a branch office for six years to provide infrastructure engineering design and consultancy, traffic engineering and related services. Direct toll collection and expressway management were not included in the approved activities.
The BBA also questioned the company's office address. BIDA records list its office at Rahman Mansion in North Badda, but an inspection reportedly found no office there. Instead, the company was found operating from the expressway's central control building in Kuril. The authority has sought clarification on whether it was authorised to use the facility.
The third issue concerns alleged violations of foreign exchange regulations and an expired trade licence. The BBA said the licence expired on June 30, 2026, without any renewal application, and questioned whether the company had met its notification requirements to Bangladesh Bank.
FDEEC had earlier said Shandong Hi-Speed was separately registered but had not been formally assigned O&M responsibilities. However, the Chinese company described itself as a contracted O&M operator in a letter dated October 29 last year.
The BBA said FDEEC's previous response was unsatisfactory and sought a detailed explanation.
The expressway is being implemented under a public-private partnership, with the BBA overseeing the project and FDEEC responsible for its operation and maintenance.