Eighth uranium shipment arrives at Rooppur plant

Published : Tuesday, 24 November, 2026 at 8:58 AM
Observer Online Report
X

The eighth shipment of nuclear fuel uranium imported from Russia has arrived at the Rooppur Nuclear Power Plant project site in Ishwardi of Pabna.

Three specialised trucks carrying the uranium entered the project site at 5:48 AM on Tuesday (November 24) under tight security provided by the army and law enforcement agencies.

With this latest delivery, a total of eight shipments have arrived in Bangladesh, including one additional shipment for Unit 1 and seven for Unit 2 of the Rooppur project.

Earlier, Russia's state-owned nuclear corporation Rosatom said it planned to supply 163 uranium assemblies for Unit 2 and 48 assemblies for refuelling Unit 1. The nuclear fuel is scheduled to be delivered to Bangladesh in a total of nine shipments.

Meanwhile, Unit 1 of the Rooppur Nuclear Power Plant has begun its second round of experimental electricity supply to the national grid.

The operation started at 10:20 AM on Monday (November 23). During this phase, the plant will undergo tests to supply 300-350 megawatts of electricity over a period of 10 to 24 hours.

Earlier, Unit 1 was connected to the national grid for the first time on November 17. Electricity generation was temporarily suspended at 11:50 PM that day after more than eight and a half hours of continuous operation. The unit generated a maximum of 375 megawatts during that period.

Science and Technology Minister Fakir Mahbub Anam said Bangladesh had emerged as the world's 33rd nuclear-powered country following the successful tests. The plant supplied up to 350 megawatts of electricity to the national grid. The output was later reduced and stabilised at 300 megawatts to maintain grid stability.

Project Director Dr Md Kabir Hossain said the second phase of experimental electricity supply would continue for 10 to 24 hours.

Under the agreement with the Russian contractor, commercial electricity generation from Unit 1 will begin gradually at full capacity after a 10-month trial operation.

Built with Russian technology, the Rooppur Nuclear Power Plant has two VVER-1200 reactor units, each with a generation capacity of 1,200 megawatts. Once both units become fully operational, the plant will be capable of generating a total of 2,400 megawatts of electricity.

The power plant is expected to play an important role in meeting the country's electricity demand and ensuring energy security.

-MT 


Advertisement
Loading...
Loading...
Editor : Iqbal Sobhan Chowdhury
Published by the Editor on behalf of the Observer Ltd. from Globe Printers, 24/A, New Eskaton Road, Ramna, Dhaka.
Editorial, News and Commercial Offices : Aziz Bhaban (2nd floor), 93, Motijheel C/A, Dhaka-1000.

Phone: PABX- 41053001-06; Advertisement: 41053012; 01793317829, 01550707291, 01550707296
E-mail: [email protected], [email protected]. [email protected], [email protected], [email protected], ‍[email protected], Online-email: [email protected]

🔝