Rooppur Nuclear Power Plant has begun supplying electricity to the national grid on a trial basis for the second time, starting at 10:20 AM on Monday (November 23).
Project Director Dr Md Kabir Hossain confirmed the development, stating that the experimental supply will continue for 10 to 24 hours, with plans to feed 300 to 350 megawatts (MW) of electricity into the national grid during this phase.
Earlier, on Tuesday (November 17), following a long wait, sequential technical operations, and multi-stage complex testing, electricity generated from Bangladesh's first nuclear power plant was experimentally connected to the national grid for the first time, delivering 350 MW from its first unit.
According to a press release issued that day, the initial supply commenced at 3:00 PM in the presence of Science and Technology Minister Fakir Mahbub Anam.
Under the scheduled plan, the initial test connection ran for roughly eight to 10 hours to evaluate the performance and stability of the plant's turbines, generators, and integrated grid synchronization, after which the unit was disconnected for further technical inspections.
At every stage of testing, engineers are closely verifying the functionality of the plant's systems, turbine and generator output, and coordination with the national grid. Once these technical evaluations yield satisfactory results and all scheduled tasks for this stage are completed, approval from the Bangladesh Atomic Energy Regulatory Authority (BAERA) will be required before proceeding to the next phase of experimental operation.
Subject to BAERA's clearance, the plant will be reconnected to the national grid to advance further testing phases.
Under the agreement with the Russian contractor, once a 10-month trial run is completed, the first unit will begin permanent commercial electricity supply at full capacity. At that stage, the Bangladesh Atomic Energy Commission (BAEC) will take provisional handover of Unit-1 from the Russian contractor, after which the Nuclear Power Plant Company Bangladesh Limited (NPCBL) will formally begin operations as the designated operating organisation via a government gazette notification.