Kalurghat-Chaktai Marine Drive opens in Dec

Published : Monday, 30 November, 2026 at 12:00 AM
Nurul Amin
CHATTOGRAM, Nov 29: The authorities of Chattogram Development Authority (CDA) have taken a step to open 9.5 kilometre-long the much-awaited Kalurghat-Chaktai four-lane Marine Drive to vehicular traffic by December, said Project Director Engineer Rajib Das.  

About 95 percent of the construction work of the project has already been completed, he said.  The embankment-cum-marine drive along the western bank of the Karnaphuli River is being constructed at a cost of Tk 2,275 crore.  Rajib Das said, a four-kilometre walkway from Kalpolok at Chaktai to Bolirhat has already been completed.

The embankment road is 80 feet in width and 24.5 feet above sea level. The project is being implemented in line with the 1995 Chattogram Metropolitan Master Plan.  Twelve high-tide protection regulators and pump houses have already been installed at canal mouths to facilitate efficient drainage of rainwater.

Construction of the project began in June 2019 with the inauguration of a sluice gate at the Chaktai Canal estuary. The government later granted a one-year extension, setting June 2026 as the revised completion deadline.


Advertisement
Loading...
Loading...
Advertisement
Editor : Iqbal Sobhan Chowdhury
Published by the Editor on behalf of the Observer Ltd. from Globe Printers, 24/A, New Eskaton Road, Ramna, Dhaka.
Editorial, News and Commercial Offices : Aziz Bhaban (2nd floor), 93, Motijheel C/A, Dhaka-1000.

Phone: PABX- 41053001-06; Advertisement: 41053012; 01793317829, 01550707291, 01550707296
E-mail: [email protected], [email protected]. [email protected], [email protected], [email protected], ‍[email protected], Online-email: [email protected]

🔝