Legal action will be taken if specific complaints are received of excessive collection of money in the name of leasing or harassment of traders from vehicles carrying sand, limestone and coal, Road Transport and Bridges Minister Sheikh Rabiul Alam has said. He said action would be taken against anyone involved in irregularities or collecting money beyond the prescribed rates under the pretext of leasing.
The issue was raised through a supplementary question by Kamruzzaman Kamrul, a ruling party Member of Parliament from Sunamganj-1, during Tuesday's session of the Jatiya Sangsad. Presided over by Speaker Hafiz Uddin Ahmed, the session heard the lawmaker allege that the practice of collecting arbitrary tolls at various locations, which began during the previous Awami League government, had yet to stop. Money is being collected at multiple points within a distance of less than one kilometre from vehicles carrying sand, limestone and coal.
In response, the minister said that the terminals under the Bangladesh Inland Water Transport Authority (BIWTA), which are used for passenger crossings, are leased through a regular process to generate government revenue. There are provisions for collecting lease fees at prescribed rates, and the leasing process is established and transparent.
However, if there are complaints of collecting money beyond the fixed rates or any other irregularities, specific information must be provided. He also said action would be taken against anyone who harasses traders after obtaining a lease.
In response to a question from ruling party MP Mohammad Mazharul Islam, the Shipping Minister said the government has taken an initiative to purchase two high-capacity rescue vessels, each with a minimum lifting capacity of 2,000 tonnes, to strengthen rescue operations on the country's rivers and maritime routes.
A project has been undertaken to procure supporting vessels, equipment and necessary infrastructure for this purpose. The feasibility study of the project was completed in 2019 by the Bureau of Research, Testing and Consultation (BRTC) of the Bangladesh University of Engineering and Technology (BUET).
Efforts are underway to secure financing from foreign development partners for implementing the project. Initiatives have been taken to seek assistance from Japan, South Korea and the Netherlands.
He said the project has also been included in the list of projects awaiting approval under South Korea's Economic Development Cooperation Fund (EDCF) for the 2025-2027 period.
3.6 Million Cubic Metres of Dredging Completed at Matarbari Port
Construction work under the Matarbari Port Development Project is progressing according to the scheduled timeline. Approximately 3.6 million cubic metres of dredging have already been completed in the project area, Minister Sheikh Rabiul Alam informed Parliament.
He said work on two of the project's three major packages has begun. Alongside the civil works for port construction, land reclamation, construction of geotube embankments and sand filling are underway.
Once implemented, the project will enable container ships with a capacity of 8,200 TEUs to berth at the port's jetty. The project is scheduled to be completed by December 2029. Therefore, he claimed, there is no delay in the establishment of the port.
The minister further informed Parliament that approximately Tk 15.8 billion was allocated under the revenue budget for river dredging from the 2009-2010 to the 2023-2024 fiscal years.
The funds have been used for maintenance dredging to keep various important waterways and ferry routes across the country operational, including Aricha-Kazirhat-Baghabari, Barishal-Bhola and Ilisha-Majuchowdhury's Hat.