Why is full-fledged take-off still delayed?

Published : Wednesday, 18 November, 2026 at 12:00 AM
More than three years after its ceremonial inauguration, the third terminal of Hazrat Shahjalal International Airport (HSIA) is still struggling to take off, with unresolved contractual arrangements, technical preparations and operational challenges standing in the way of its full-fledged commercial launch.

Despite being one of the country's largest aviation infrastructure investments, the Tk22,213 crore facility is preparing for only a limited start on December 16, initially handling four flights a day. Full operations are now expected by March or April 2027, reflecting the scale of difficulties in turning a completed infrastructure project into a fully functional international terminal.

Designed to handle 12 million passengers annually, with provisions for further expansion, the terminal was inaugurated in October 2023 under the previous government. However, it has remained largely idle because of incomplete equipment installation, systems integration and unresolved operational arrangements.

The government is now pursuing a phased opening, directing the Civil Aviation Authority of Bangladesh (CAAB) and other agencies to complete preparations before the December deadline. These include immigration facilities, baggage conveyor systems, scanners and operational trials.

The prolonged delay has also created a financial burden, with the massive investment yet to generate the returns expected from its commercial operation.

CAAB has already paid Tk1,100 crore from its own earnings and faces another payment obligation of Tk900 crore, according to the minister. The authority has been relying on revenue from existing airport operations to meet its financial commitments while the new terminal remains largely unused.

The operating agreement with the Japanese consortium has emerged as another major challenge. Bangladesh's share of terminal revenue was increased from 15 per cent to 27 per cent following negotiations, but the long-term financial implications of the arrangement remain a matter of concern.

The concession agreement is still undergoing scrutiny, with legal and financial approvals required before the operating framework can be finalised. The delay in settling these arrangements has added uncertainty to the terminal's transition into commercial operations.

Ground handling has emerged as another contentious issue. Four international companies - Britain's Menzies Aviation, Switzerland's Swissport, Türkiye's Çelebi Aviation and the UAE's dnata - have been shortlisted to provide services at the new terminal.

Their possible entry could reshape a sector traditionally dominated by Biman Bangladesh Airlines. The proposed operators are expected to meet technical, security and service requirements before receiving regulatory approval.

The introduction of international operators is expected to improve baggage handling, aircraft turnaround and passenger services. However, questions remain over Biman's future role, employment arrangements and the enforcement of service standards.

The government has also indicated that baggage delivery will be subject to specific performance targets, with penalties for operators failing to meet prescribed standards. Effective monitoring will be essential to ensure that these commitments translate into better passenger services.

The terminal comes with modern passenger facilities, expanded aircraft parking, high-speed taxiways and separate cargo infrastructure. However, the additional capacity may not fully address the airport's longer-term congestion.
Hazrat Shahjalal International Airport will continue operating with a single runway, limiting its ability to accommodate rapidly increasing air traffic despite the expansion of terminal facilities.

For a project that has absorbed Tk22,213 crore and remained largely unused for years, the December 16 launch will be an important step. But starting a limited number of flights is only the first challenge.

The bigger test will be resolving outstanding contractual and financial issues, ensuring accountability among service providers and establishing an effective operating system capable of delivering the benefits promised by one of the country's largest aviation investments.



Advertisement
Loading...
Loading...
Editor : Iqbal Sobhan Chowdhury
Published by the Editor on behalf of the Observer Ltd. from Globe Printers, 24/A, New Eskaton Road, Ramna, Dhaka.
Editorial, News and Commercial Offices : Aziz Bhaban (2nd floor), 93, Motijheel C/A, Dhaka-1000.

Phone: PABX- 41053001-06; Advertisement: 41053012; 01793317829, 01550707291, 01550707296
E-mail: [email protected], [email protected]. [email protected], [email protected], [email protected], ‍[email protected], Online-email: [email protected]

🔝